What this case file does
Big projects start with a public plan: so many homes, a hotel, a price. This case file puts the first plan for five places next to what was approved or paid for later. Each item is labeled approved, proposed, authorized or issued.
Nordic Valley
In 2022, a news report said up to 550 homes. It did not mention public money. Later reports say 637 housing units and 230 hotel rooms.
Nordic Valley, then and now
Utah Business (2022); KSL (2024); Deseret News (2026).
The county also created three public infrastructure districts, called PIDs. Together they can borrow up to $240 million. They repay it with a tax on property inside the districts. By June 30, 2026, the first district's books showed about $54.5 million in bonds owed.
Powder Mountain
A 2008 county record lists a fire station on the mountain and support for a second, seasonal emergency road off it. The fire station broke ground in September 2026. Powder Mountain is paying the $6 million. The second road has not been built.
On Sept. 8, 2026, the county planning board approved two plan changes 5 to 0. They were handled as administrative items, which do not go to the County Commission.
Eden Crossing
In 2023, the County Commission approved this project 2 to 1. Its advisory board had voted 5 to 2 to deny it. In 2025, the commission added 8.73 acres, 3 to 0. The minutes say density did not go up. The state has not yet decided its latest water request.
Longhorn and West Creek
Longhorn was allowed up to 116 lots. Then 22 unused lots were moved to the owner's next-door project, Meibos. The county approved that in March 2026.
Where Longhorn's lots went
County staff report and minutes, 2026.
A new rezone for West Creek, next door, came up at two planning work sessions. No vote is taken at a work session.
Snowbasin
Snowbasin's districts can borrow up to $300 million. Their draft 2026 budgets list no debt.
How the changes were decided
Some later changes got a public vote. Others did not: administrative plan changes, and a financing district the landowners formed themselves with the protest time waived. The costs of fire trucks, roads and water are shared by the wider public.
What is still open
We have not found Powder Mountain's total allowed units under its 2015 agreement. We also do not know who pays the other half of Nordic's ladder truck. The plan pays half, $1 million. A Weber and Cache County services deal for the Powder Mountain area was on the County Commission's October agendas. We did not find the outcome.
Our grades
Power D. Transparency C. Financial accountability D+. Environmental impact D. Community impact C−. Each project's first approval had a public vote or hearing.
What this page does not say
This page does not say anyone broke a law. It shows what the public records say.