CASE FILE · OGDEN RDA · CONTINENTAL CRA · OC 006

WonderBlock: the bonds and the parking

Ogden's biggest recent downtown project, on the old Wonder Bread site at 26th Street and Grant Avenue, from the votes to the paid parking that helps pay for the garages.

Project area: Continental CRAVotes: Jan. 10, 2023Developer: J. Fisher Companies

Posted Nov. 6, 2026

WHERE
26th Street and Grant Avenue, downtown Ogden

In plain words

Ogden's redevelopment agency bought the old Wonder Bread plant in 2016, cleared it, and in 2023 agreed to a joint project with a private developer. The city borrowed for two things: part of the project, repaid from future sales tax and the extra property tax the project creates, and two parking garages, repaid through a lease. To help pay for the garages, the council approved paid parking downtown in May 2026. Property owners keep paying their full tax bill; for the life of the project area, the agreed share of the growth in those taxes goes to the RDA instead of the taxing entities' budgets.

Explain it like I'm 10

The short version

The 2023 votes

DateBodyWhatVote
Jan. 10, 2023Redevelopment AgencyResolution 2023-1: sales tax and tax increment revenue bonds, not to exceed $75,000,0004–3
Jan. 10, 2023Municipal Building AuthorityMaster lease and lease revenue bonds, not to exceed $85,000,0005–2
Jan. 17, 2023Redevelopment AgencyCourt parking agreement, operating agreement, land transfer and development agreementApproved

The meeting results list totals only. Who voted which way isn't in the documents read for this page.

Paid parking

On May 5, 2026, the council approved downtown paid parking, 5–2. KSL reported street rates of $1.50 to $2 an hour, off-street rates of $1 to $1.50, $10-a-month permits for downtown workers, and fees starting about June 15, 2026 after a trial period. KSL reported the garage bonding at about $60.13 million, and that parking revenue will cover garage operating costs and help cover the bond payments. When the bonds were approved in 2023, a city flyer said the projects "will not use funds from the property taxes of Ogden residents" (KSL, Jan. 11, 2023).

Timeline

2016–2024 dates are from the RDA's Sept. 10, 2024 work session staff review.

Map

People connected to the record

J. Fisher CompaniesDeveloperParty to the 2020 and restated 2023 land transfer and development agreements.
Ogden RDA board / City CouncilApproved the bonds and agreementsSame seven members sit as the RDA board and the Municipal Building Authority.
Brandon CooperCommunity & Economic Development Director (2023)Quoted by KSL on the project in Jan. 2023.

What we don't know yet

  • How each member voted on the 2023 bonds and the 2026 paid parking vote.
  • How much of each bond has been issued so far, and at what rates. (Earlier Hive reporting cited $64.22 million in Series 2023 RDA bonds; that figure wasn't re-checked for this page.)
  • How much paid parking has brought in since it began, and how that compares with the garage payments.
  • Which J. Fisher entity signed each agreement. Earlier Hive research found two Utah companies named "J. Fisher Companies, LLC"; that hasn't been re-checked for this page.

Every item above is also a question you can ask. See Questions to ask, and whom to ask.

Questions to ask, and whom to ask

  1. Ogden RDA / Community & Economic Development: How much of the $75 million and $85 million authorizations has been issued, and what are the annual payments?
  2. City Council: Will the city report paid-parking revenue against the garage bond payments each year?
  3. Ogden City Recorder: Do the approved minutes for Jan. 10, 2023 and May 5, 2026 show how each member voted?
  4. Ogden RDA / Community & Economic Development: Which J. Fisher company, by state entity number, signed each WonderBlock agreement?

Words to know

Where this connects

Behind this piece

3
city documents read
2
news reports
9
dates on the timeline

Posted Nov. 6, 2026. Built from Ogden City Council/RDA/MBA meeting results (Jan. 10, 2023), the RDA's Sept. 10, 2024 staff review, the RDA's January 2025 annual update, and KSL reporting.

Help cover records costs

Public records aren't always free. The Hive Records Fund helps pay records fees, copies and other costs behind pages like this one. You pick the amount, and every dollar in and every cost paid is listed publicly. The Weber County Hive is not a nonprofit, so contributions are not tax-deductible.

Give to the Records FundSee the public ledger →

Sources

Sources — click to open (with links)
Utah Hive Politicsfrom the publisher of The Weber County HiveIndependent · Accountability · Journalism

The Weber County Hive and Utah Hive Politics: the people's publication. We investigate what's best for the public as a whole, not for any party or special interest group. We report public records. You decide.

Send a tipTips we checkedSee a mistake? Tell us

We never name tipsters. When we correct a page, the fix and its date are shown on the page.

Ogden City shelf · Master Index (Hive library) · Read on Substack